Project Network Diagrams Explained

Behind every Gantt chart there is a quieter picture that decides where the bars land: the project network. It maps each activity and the links between them, then runs two simple sweeps to find the earliest and latest each task can happen. From those numbers fall the float, the critical path, and the bars you actually see. This guide walks through the precedence diagramming method, the four dependency types, and a worked forward and backward pass on a small real network.

By Uttam Regmi

A precedence network draws activities as nodes and dependencies as arrows, with the critical path running straight through:
A precedence network (activity-on-node)ABCDEFcriticalhas float

What a network diagram really is

A project network diagram is a map of the logic in your plan. It strips away the calendar and the bars and shows only two things: the activities that make up the work, and the dependencies that say which activity has to wait for which. Everything else in scheduling, including the dates on a Gantt chart, is computed from that map.

The value of drawing it is that logic errors become obvious. A missing link, a task that depends on nothing, a loop where two tasks each wait for the other: these hide easily in a list of dates but stand out at once in a network. Get the network right and the schedule almost builds itself. Get it wrong and no amount of careful date entry will save the plan.

Two notations, one survivor

Historically there were two ways to draw a network. The older activity-on-arrow method put activities on the arrows and used nodes as connection points. It was fiddly, often needing invisible dummy arrows just to express certain links, and it has largely disappeared from modern practice.

The method that won is activity-on-node, better known as the precedence diagramming method, or PDM. In PDM each activity is a box, or node, and each arrow is a dependency between two activities. Every scheduling tool you are likely to touch today uses PDM under the hood, so it is the notation worth learning. The rest of this guide is entirely about it.

Nodes as activities, arrows as dependencies

In PDM the node carries the work. A node holds the activity name and its duration, and once the passes are run it also holds four computed dates plus the float. The arrow carries the rule. An arrow drawn from activity A to activity B says B depends on A, so B cannot happen freely until A has done its part.

Read that direction carefully, because it is the whole grammar of the diagram. The tail of the arrow is the predecessor. The head is the successor. A node with no incoming arrows can start immediately. A node with no outgoing arrows is a finish point of the project. The shape of the network is simply the set of all these predecessor and successor relationships drawn at once.

Finish → StartABB waits for AStart → StartABB waits for AFinish → FinishABB waits for AStart → FinishABB waits for A
How each arrow encodes a predecessor to successor rule between two activity nodes

The four dependency types

Not every dependency is the plain "finish this, then start that" link. PDM supports four types, defined by which end of the predecessor connects to which end of the successor. Finish-to-start is by far the most common, but the other three exist because real work overlaps.

TypeRuleEveryday example
Finish to start (FS)Successor starts after predecessor finishesPour the foundation, then build the walls
Start to start (SS)Successor starts after predecessor startsBegin paving once grading has begun
Finish to finish (FF)Successor finishes after predecessor finishesTesting wraps only when coding wraps
Start to finish (SF)Successor finishes after predecessor startsOld shift ends once the new shift starts

For a deeper tour of when each one earns its place, see the guide on task dependencies. For the worked pass below we use only finish-to-start links, which keeps the arithmetic clean while showing the whole method.

Building the network step by step

You do not need special software to sketch a network. A whiteboard and sticky notes work, and the discipline of doing it by hand often surfaces missing logic. The sequence is always the same.

  1. List every activity that has to happen, one per node, with an honest duration on each.
  2. For each activity, ask what must be done before it can begin, and draw an arrow from each of those predecessors into it.
  3. Check that at least one node has no predecessor, so the network has a start, and at least one has no successor, so it has an end.
  4. Scan for loops, where following the arrows brings you back to where you started, and break any you find, because a network cannot contain a cycle.
  5. Run the forward pass to get the earliest dates, then the backward pass to get the latest dates.
  6. Subtract to get the float, and mark the zero-float chain as your critical path.

Steps five and six are the mechanical heart of the method, so the next two sections walk through them on a concrete example.

The forward pass: earliest dates

The forward pass sweeps left to right and answers the question, how soon can each activity happen? It produces two numbers per node: the early start (ES) and the early finish (EF), where EF is simply ES plus the duration. The rule for ES is that an activity cannot start until every predecessor has finished, so its ES is the largest EF among the activities feeding it.

The network. Six activities: A Requirements (3 days), B Design (4, after A), C Backend (6, after B), D Frontend (5, after B), E Integrate (3, after C and D), F Launch (2, after E). Counting from day 0, each early finish is its early start plus its duration.

Sweeping forward. A starts at 0 and finishes at 3. B starts at 3, finishes at 7. B then feeds both C and D, so each starts at 7: C finishes at 13, D finishes at 12. E waits for the later of C and D, so its start is 13, not 12, and it finishes at 16. F starts at 16 and finishes at 18.

The result. The whole project needs 18 days. That single number, the largest early finish in the network, is the shortest time in which the work can possibly be done.

The backward pass: latest dates

The backward pass sweeps right to left and answers the mirror question, how late can each activity happen without pushing out the finish? It produces the late finish (LF) and late start (LS), where LS is LF minus the duration. You seed it by setting the final activity's LF equal to its EF from the forward pass, then work back. The rule for LF is that an activity must finish before its earliest successor needs to start, so its LF is the smallest LS among the activities that depend on it.

Seeding the end. F is the finish, so its LF equals its EF of 18, and its LS is 16. E must finish before F starts, so E has LF 16 and LS 13.

Working back through the branch. Both C and D feed E, so each takes LF 13. C, at 6 days, has LS 7. D, at 5 days, has LS 8. B feeds both C and D, so its LF is the smaller of their late starts, that is 7, giving B an LS of 3. A feeds B, so A has LF 3 and LS 0.

What the gap reveals. D can start as late as day 8 but as early as day 7, so it has room to slide. Every other activity has its late start equal to its early start, meaning it has none.

A · 3B · 5C · 2D · 4Critical path: A → B → DSlack (C): 3Duration: 12
The zero-float chain that the forward and backward pass reveal as the critical path

Float and the critical path

Float, sometimes called slack, is the reward for doing both passes. For any activity it is the late start minus the early start, which equals the late finish minus the early finish. It is the amount of time the activity can slip before it delays something downstream. Any activity with zero float sits on the critical path, the longest chain through the network and the sequence that sets the project length.

ActivityDurationESEFLSLFFloatCritical
A Requirements303030Yes
B Design437370Yes
C Backend67137130Yes
D Frontend57128131No
E Integrate3131613160Yes
F Launch2161816180Yes

The critical path is A, B, C, E, F, whose durations add to 18. D is the only activity with slack, one day of it, because the backend it runs alongside takes a day longer. The wider theory behind these numbers lives in the guide on the critical path method, and the meaning of the slack itself in the guide on float.

How the network underlies the Gantt chart

A Gantt chart is a picture of the forward pass. Each bar is drawn from an activity's early start to its early finish, and the vertical stack of bars is just the nodes listed down the page. The dependency arrows you drag between bars in a Gantt tool are the same arrows as in the network, only bent to follow the timeline. When you move one bar and the ones after it shift, you are watching a forward pass recompute in real time.

This is why a Gantt chart that ignores dependencies is so fragile. Without the network beneath it, the bars are just decorated dates that never react to change. With the network, they behave like a model. You can build that living version, links and all, in the free Gantt maker and watch a slip cascade the moment you enter it.

How the network underlies the critical path

The critical path is not something you draw. It is something the network computes, then you read off. Once the two passes are done, the critical path is simply every node whose float is zero, joined tail to head. In our example those nodes form one unbroken chain, but larger networks can have several critical paths at once, or a near-critical path with a single day of float that becomes critical the instant an estimate grows.

Because the path falls out of the float, it moves when the logic or the durations move. Shorten the backend and the frontend might become critical instead. This is the payoff of thinking in networks rather than bars: the diagram does not just show today's critical path, it tells you which chain would take over next if reality shifts.

Common mistakes that break a network

Most broken networks fail for a handful of repeatable reasons, and all of them are easy to catch once you know the pattern. A quick review against this list before you trust the dates will save you from a plan that computes a confident but wrong answer.

MistakeSymptomFix
Dangling activityA node with no predecessor or no successor mid-planAdd the missing link so it joins the flow
Hidden loopThe tool refuses to schedule or hangsFind the cycle and remove one wrong arrow
Date instead of logicBars that will not move when a predecessor slipsReplace the fixed date with a real dependency
Over-linkingA tangle of arrows nobody can readKeep only the links that are truly required

The worst of these is the third, a hard date standing in for a dependency, because it produces a plan that looks finished yet quietly stops reacting to change. A Gantt chart built once and never touched is not a plan, it is a wish.

From diagram to a living plan

The network is not a document you draw once and file. It is the engine that keeps the schedule honest, and it only earns its keep if you let the two passes run again every time an estimate or a link changes. In a good tool that happens automatically the moment you edit a duration or drag a dependency, which is exactly why building your plan on real logic beats typing in dates by hand.

Start from the logic, not the calendar. List the activities, draw the arrows, run the passes, and read off the critical path. Do that and the dates take care of themselves, the float tells you where you have room, and the critical path tells you where you do not. That is the whole quiet power of the precedence network sitting under every Gantt chart you will ever build.

A network diagram is the logic under the bars. Draw the activities and their dependencies, run the forward and backward pass, and the float, the critical path, and the Gantt chart all fall out of the same picture.

Templates that use this

Frequently asked questions

What is the difference between a network diagram and a Gantt chart?

A network diagram shows pure logic: activities as nodes and dependencies as arrows, with no timeline. A Gantt chart places those same activities on a calendar as bars. The network computes the dates through its two passes, and the Gantt chart displays the result, so they are two views of one plan.

What does the precedence diagramming method mean?

The precedence diagramming method, or PDM, is the activity-on-node way of drawing a project network. Each activity is a box and each dependency is an arrow between boxes. It replaced the older activity-on-arrow style and is the notation every modern scheduling tool uses beneath its Gantt view today.

How do the forward and backward pass work together?

The forward pass sweeps left to right to find the earliest each activity can start and finish. The backward pass sweeps right to left to find the latest each can happen without delaying the project. The gap between the two, at each activity, is its float, and zero float marks the critical path.

What are the four dependency types?

Finish to start, where a task waits for another to finish, is the common one. Start to start links two beginnings. Finish to finish links two endings. Start to finish, the rare one, ties a successor's finish to a predecessor's start. Each connects a different end of the predecessor to the successor.

Can a network have more than one critical path?

Yes. Any chain of activities with zero float is critical, and a network can hold several such chains at once. There can also be a near-critical path carrying only a day or two of float that becomes critical the moment an estimate on it grows, which is why it pays to watch the low-float chains too.

Written by Uttam Regmi, founder of Synth88 Labs. An auditor by profession and a builder by passion, he creates privacy-first web and mobile apps from Dubai, UAE, gantts.app among them. More about the maker · LinkedIn · Medium · GitHub