HomeTemplates › EV Charging Station Installation Schedule Template

EV Charging Station Installation Schedule Template

A free EV charging station installation schedule template covering site assessment, utility coordination, permitting, civil works, equipment installation, commissioning and network activation, with the utility interconnection lead time treated as the schedule driver it usually is.

Preview of the ev charging installation schedule template showing phases across a timeline

What's included

Most EV charging projects are not delayed by the install. They are delayed by the utility. The template is sequenced accordingly:

Who uses this template

Used by EV infrastructure developers, electrical contractors, and facilities or fleet managers installing chargers at depots, retail sites, or workplaces. It sequences site assessment, utility coordination, permitting, trenching, and commissioning so the long-lead items like grid capacity and permits are tracked from day one rather than surfacing as surprises near energisation.

Utility service upgrades are the most common cause of overrun on EV charging projects, and the lead time is set by the utility rather than by you. Start the service application in parallel with design instead of after it, and keep it visible on the chart as its own track.

How to customize it

  1. Adjust the utility phase to your local provider, service upgrade timelines vary enormously by region.
  2. Duplicate the civil and install rows per site if you are rolling out multiple locations.
  3. Add DC fast-charging rows (larger switchgear, dedicated transformer) or delete them for Level 2 only.
  4. Include a make-ready allowance if you are claiming utility or government incentives with their own deadlines.
  5. Mark utility approval, permit issue and energization as milestones, each is a hard gate.

Scheduling tips

Frequently asked questions

How long does an EV charging station installation take?

Level 2 installations with adequate existing capacity can complete in 6-12 weeks. Projects needing a utility service upgrade commonly run 6-12 months, because the utility timeline dominates. The template shows both paths.

What is usually the longest lead item?

Utility service upgrades and transformers. Both are outside the installer's control, which is why the template gives utility coordination its own phase rather than folding it into permitting.

Does this work for a multi-site rollout?

Yes. Duplicate the site assessment, civil and commissioning rows per location and keep one shared procurement track, so you can see where sites compete for the same crews or equipment.

Is the EV charging schedule template free?

Yes, free downloads in Excel, PowerPoint and CSV, and free online editing with no account.