Refinery Turnaround Schedule Template

A free refinery turnaround schedule template built around the real STO lifecycle, long-range planning, scope freeze, work-package development, long-lead procurement, execution and start-up. Download for Excel, PowerPoint or CSV, or open it online to link dependencies and see the critical path that drives your return-to-service date.

Preview of the refinery turnaround schedule template showing phases across a timeline

What's included

Turnarounds are planned in months and measured in hours. The template is organized into the six stages a shutdown, turnaround and outage (STO) event actually moves through:

Who uses this template

Turnaround managers, maintenance planners, and reliability engineers at refineries and petrochemical plants use this for a major shutdown. It spans long-range planning, scope freeze, detailed work packages, execution, and start-up, coordinating thousands of tasks and contractors during the tightly costed window when the unit is offline.

The scope freeze is the single most protective date on the schedule. Late scope is the most common cause of turnaround overrun, so treat the freeze as a hard milestone with dependencies behind it, everything downstream should key off that date rather than off wishful thinking.

How to customize it

  1. Set the execution window first and work backwards, turnaround dates are usually fixed by production, not by planning convenience.
  2. Pull the scope freeze earlier if your worklist is large; 8-12 weeks before execution is common.
  3. Add discipline rows under Execution (mechanical, E&I, inspection, civil) so each contractor sees its own sequence.
  4. Load long-lead procurement against real supplier lead times, not nominal ones.
  5. Mark every permit, isolation and inspection sign-off as a milestone so nothing proceeds out of sequence.

Scheduling tips

Frequently asked questions

How far in advance should a refinery turnaround be planned?

Long-range planning for a major turnaround typically begins 18-24 months before the execution window, with scope freeze commonly 8-12 weeks out. The template lays those stages out on a timeline so you can see whether your runway is realistic.

What is a scope freeze and why is it on the schedule?

The scope freeze is the point after which no new work is added to the turnaround worklist. It appears as a milestone because late scope is the most common cause of overrun, everything after it depends on the worklist being stable.

Can I show dependencies between turnaround activities?

Yes. Open the template in the free gantts.app editor to link finish-to-start relationships across isolation, inspection and repair, so downstream work shifts automatically and the critical path stays visible.

Is the refinery turnaround template free?

Yes, free to download as Excel, PowerPoint or CSV, and free to edit online with no sign up.