What's included
Apparel schedules are built backwards from the delivery window, and the sample rounds are what consume the runway. The template follows the standard T&A sequence:
- Concept & design, Range planning, design finalization, fabric and trim selection, and the tech pack that everything downstream depends on.
- Sampling, Proto sample, fit sample and pre-production (PP) sample, each with a comment-and-revise loop. Milestone: PP sample approved.
- Materials, Fabric booking, lab dips and strike-offs, trim ordering and in-house inspection. Milestone: fabric in-house.
- Pre-production, Marker making, pattern grading, size set and the PP meeting that releases the line.
- Bulk production, Cutting, sewing, in-line QC, finishing and pressing.
- Finishing & shipment, Final inspection, packing, ex-factory and transit to the delivery window. Milestone: ex-factory.
Who uses this template
Apparel product developers, sourcing managers, and production coordinators at brands and factories run a time-and-action (T&A) calendar each season. It tracks the critical path from tech pack and proto through fit and PP samples, bulk fabric, cutting, and sewing to the ex-factory date, flagging slippage early so shipments hit retail windows.
Timeline at a glance
Typical durations for each phase, as a planning starting point. Real timelines vary with scope, resources, approvals and how much work runs in parallel, so adjust the bars to your own project.
| Phase | Typical duration | Key milestone |
|---|---|---|
| Design & development | 6-10 weeks | Line finalised |
| Sampling & approval | 4-8 weeks | Samples approved |
| Sourcing & costing | 3-6 weeks (overlaps) | Materials booked |
| Bulk production | 8-14 weeks | Goods produced |
| QC & shipping | 2-4 weeks | Goods shipped |
| In store | Season | On sale |
How to customize it
- Set the delivery date and work backwards; apparel calendars are countback calendars.
- Adjust sample rounds, some buyers require additional fit rounds, each adding two to three weeks.
- Extend fabric lead time for mill-dyed or specialty fabrics, which dominate the early calendar.
- Add rows per style or per colourway if you are running a multi-style drop.
- Include a shipping mode row; sea freight adds weeks that must sit inside the calendar.
Scheduling tips
- Count back from ex-factory, not from delivery. Transit time is fixed and non-negotiable, so ex-factory is your real deadline.
- Fabric is usually the long pole. Booking, dyeing and shipping fabric routinely takes longer than sewing the garment.
- Build in buyer comment time. Sample approvals wait on someone else's calendar; two weeks per round is realistic.
- Protect the size set. Skipping it to save days almost always costs more in bulk re-work.
- Track by style. A drop is only as ready as its slowest style, which an aggregate bar hides.
Related templates
- Free Content Calendar Gantt Chart Template
- Free Product Launch Gantt Chart Template
- Project Management Gantt Chart Template
- Browse all Gantt chart templates
Frequently asked questions
What is a time and action (T&A) calendar?
The apparel industry term for a production schedule that counts backwards from the delivery date through ex-factory, production, sampling and materials. This template is a T&A calendar in Gantt form.
How long before delivery should an apparel calendar start?
Commonly 4-6 months for a standard order, longer for mill-dyed fabric or complex construction. Sampling and fabric lead time consume most of that runway.
What usually delays a garment order?
Fabric lead time and sample approval rounds, far more often than sewing capacity. Both get their own tracked phases in the template.