Hotel Refurbishment Schedule Template

A free hotel refurbishment schedule template for a hotel that stays open while it is being rebuilt, phased floor-by-floor closures, the room-night revenue lost in each one, noise windows around guest hours, lift and back-of-house sequencing, and public area works timed to the low season. Download it for an owner or asset manager, or open it online to see how many keys you are actually taking out of inventory each month.

Preview of the hotel refurbishment schedule template showing phases across a timeline

What's included

A refurbishment of a trading hotel is a construction project with a revenue meter running next to it. The template sequences the work around occupancy rather than around trade availability:

Who uses this template

Hotel owners, asset managers, and refurbishment contractors use this to renovate an operating property while it stays open. It phases floor closures, manages room-night loss, and schedules noisy works, lift upgrades, and back-of-house jobs into windows that protect guests, balancing the pace of works against lost revenue and comfort.

Price every closure in room-nights before you sequence anything. A floor of 30 keys closed for eight weeks is roughly 1,700 room-nights of lost inventory, and moving that closure from July to February can be worth more than the entire contractor saving you were negotiating. The displacement model belongs at the front of the schedule, not in an appendix.

How to customize it

  1. Replace the floor rows with your own key counts and closure lengths, then total the room-nights lost per month against your forecast.
  2. Shift public area works into your genuine low season, for most hotels that is a narrower window than the annual budget implies.
  3. Set the noisy-works window to the hours your operations team can actually defend, and keep drilling and demolition inside it.
  4. Add a lift row per car; modernising them simultaneously is almost never acceptable in an operating hotel.
  5. Insert a decant plan if you have to relocate guests mid-stay, and staff it, it is real front-office work, not a rounding error.
  6. Mark capital approval, mock-up sign-off, last floor handback and full inventory restored as milestones.

Scheduling tips

Frequently asked questions

How long does a hotel refurbishment take?

A phased refurbishment of a mid-sized operating hotel commonly runs 12-24 months, because floors are closed in sequence rather than all at once. The template uses an eighteen-month schedule you can compress by closing more keys at a time, at a revenue cost.

Should the hotel close completely instead?

Sometimes, and the displacement model is what tells you. A full closure is faster and cheaper to build but surrenders all revenue and risks losing corporate accounts and staff. Model both before committing; this template is built for the phased option.

How do I schedule noisy work in an operating hotel?

Agree a fixed daily window, typically mid-morning to late afternoon, and treat it as a hard constraint on the programme rather than a request to the contractor. Drilling, demolition and core cutting outside that window is what drives complaints and rate compensation.

How is this different from the pre-opening template?

This one is for a hotel that is trading now. If you are commissioning a brand new property with no guests to protect, use the hotel pre-opening critical path instead, it is organised around opening readiness rather than around closures.

Is the hotel refurbishment template free?

Yes. Free Excel, PowerPoint and CSV downloads, and free online editing with no account and no watermark.

Plan it online, free

Open this template in the editor, drag the bars to fit your dates, and export to PDF, Excel or PowerPoint. No account, no watermark.

Open the free editor