HomeTemplates › Tunnel Construction Schedule Template

Tunnel Construction Schedule Template

A free tunnel construction schedule template built around the machine rather than around the phases, TBM specification, manufacture, factory acceptance and shipping as a long lead that starts before the ground is broken; a launch shaft that has to be finished, not nearly finished, to receive it; an advance rate that changes with the ground; segment supply and muck haulage as continuous services that gate the drive; then breakthrough, secondary lining and the ventilation and fire systems that follow it. Download it for a stage-gate pack, or open it online and set your own metres per week.

Preview of the tunnel construction template showing phases across a timeline

What's included

A tunnel programme is not a sequence of trades. It is one machine moving forward at a rate the ground allows, with everything else arranged to keep it moving. The template is organised that way:

Who uses this template

Tunnelling engineers, underground construction managers, and major-infrastructure planners use this for bored and mined tunnels. It tracks TBM manufacture and delivery, the launch shaft, advance rates, cross-passages, breakthrough, and fit-out, so the long lead on a tunnel boring machine and steady daily progress are planned around one of the costliest items in the programme.

The TBM is the schedule. Order it late and nothing you do afterwards recovers the time: design, manufacture, factory acceptance and shipping run 12-18 months on a bespoke machine, and it cannot be lowered into a shaft that is not finished. The two bars that ruin tunnel programmes are the manufacture bar starting too late and the shaft bar finishing after the machine arrives, a machine sitting in pieces on the surface costs money every day and buys nothing. Put both on the chart on day one and never let them drift.

How to customize it

  1. Set your advance rate from the geotechnical baseline report, not from the best week on your last job, then split the drive into separate bars per ground unit so a bad reach is visible rather than averaged away.
  2. Give the first few hundred metres its own short, slow bar. Every TBM has a learning curve while the crew, the grouting and the spoil system settle down, and planning it at full rate is a guaranteed early slip.
  3. Add a hyperbaric intervention bar wherever the baseline predicts abrasive ground. Cutter tool changes are planned events with a known duration; discovering them mid-drive is what turns them into a month.
  4. Model segment supply as a continuous bar running the length of the drive, and check the casting yard output against your peak weekly ring count rather than the average.
  5. Show muck removal and the spoil disposal route explicitly. A full spoil bin or a lost tip licence stops the machine as effectively as a mechanical failure.
  6. Mark consents granted, TBM contract awarded, launch shaft ready, TBM ready to launch and breakthrough as milestones, those five dates are the whole programme in summary.

Scheduling tips

Frequently asked questions

How long does it take to build a tunnel?

A single-bore urban tunnel of a few kilometres commonly runs 30-40 months from consent to handover, which is roughly what the template uses. The variance is in TBM lead time at the front and ground conditions during the drive.

How far ahead should I order the TBM?

Design, manufacture, factory acceptance and shipping typically take 12-18 months for a bespoke machine, and assembly underground adds more. The order has to be placed while the shaft is still being designed, not when it is finished.

How do I schedule an advance rate I cannot predict?

Split the drive into bars per ground unit from the geotechnical baseline report and give each one its own rate. That way a slow reach shows as a slow reach rather than being hidden in a single averaged bar.

Why does the schedule slow down at the start of the drive?

Every drive has a learning curve. The crew, the ring build cycle, the grouting and the spoil handling all take a few hundred metres to settle, and planning the first weeks at full production rate is a common early overrun.

When should cross-passages be built?

After the machine has passed and the rings through that reach are grouted, but usually while the drive continues ahead. They need ground treatment first and they carry the highest risk on the job, so they get their own bars rather than being treated as float-filling work.

Is the tunnel construction template free?

Yes. Free Excel, PowerPoint and CSV downloads, and free online editing with no account and no watermark.

Plan it online, free

Open this template in the editor, drag the bars to fit your dates, and export to PDF, Excel or PowerPoint. No account, no watermark.

Open the free editor